Managing precedence constraints in the Gantt view

You can manage precedence constraints from the Gantt view to ensure that tasks are completed in a designated order.

About this task

A precedence constraint is a relationship between two work records that indicates when one task begins or ends in relation to another. You can define precedence relationships between any tasks that are siblings under the same parent work record. Some precedence relationships are defined in the Changes application where the work record originated. You can edit constraints or add new ones in the Gantt view.

Procedure

  1. To insert a precedence constraint, click Insert Constraint Insert Constraint icon. The cursor changes to a cross shape.
    Note: To turn off the Insert Constraint button without inserting a constraint, press the Escape key.
  2. In the Gantt chart, click the first task in the constraint relationship that you want to define, then click the second task.
  3. Right-click on the red line for the constraint that you inserted. Select Edit Constraint.
  4. In the Edit Constraint window, select the constraint type you want to create. Then, enter any lead or lag time you want to include between tasks. For example, if you want to create a one hour delay between when task 1 ends and task 2 begins, create a Finish to Start relationship between task 1 and task 2, with a one hour lag.
  5. To delete a constraint, select the constraint in the Gantt chart, and then click Delete ConstraintDelete Constraint icon.
  6. Click Save Schedule.Save icon
  7. To save your changes to the work records in the work management applications, click Commit ChangesCommit Changes icon from the toolbar.