PMCHGFLEXD1 workflow details
The PMCHGFLEXD1 express workflow completes only the steps for the current phase, updates the status, and exits. The user clicks the workflow icon () again to start the next step in the process.
This workflow performs the same process steps as the other express workflow, PMCHGFIXD1. However, the PMCHGFLEXD1 workflow is more flexible than PMCHGFIXD1; for example, you can go back and change the status to an earlier phase in the process and redo that earlier phase. Because you click the workflow icon to move from step to step, you have more control over the step-by-step process.
This workflow is operational when the workflow icon () is linked to it. When you click this icon, or when you check Start Change process workflow in the New Change dialog, the workflow starts processing the Change. The icon changes to to indicate that the Change is in progress. After the Change is completed, the icon changes back to .
The following table describes the actions that are performed when you click the workflow icon at various times during the process. Each phase of the Change is discussed more fully in the phase-related sections of the information center.
If you click when these conditions apply... | The PMCHGFLEXD1 workflow does the following: |
---|---|
The internal value of the Change status is not WAPPR, APPR, INPRG, or COMP | Displays a dialog informing you that the Change
process is complete. Examples of valid status values: WAPPR, ASSESS, SCHED, AUTH, IMPL, COMP, REVIEW Example of invalid status values: CLOSE, FAILPIR, CAN, REJECTED |
The status has a valid value | Turns off flow control. |
The Change has no owner or owner group | Sends an assignment to the workflow initiator,
who can do either of two things:
|
The status is WAPPR, and the Change is a standard Change | Sets the authorization decision to Preapproved, sets the status to IMPL (implementation), and issues the needed implementation assignment or assignments. |
The status is WAPPR, and the Change is a normal or emergency Change | Sets the status to ASSESS (assessment). |
The status is ASSESS | Sends assessment assignment to the Change owner or owner group. After the assessment is complete, sets the status to SCHEDULE. |
The status is SCHEDULE | Sends a scheduling assignment to the Change owner or owner group. After scheduling is complete, sets the status to AUTHORIZE. |
The status is AUTHORIZE, and the Authorization Decision field contains the value Approved or Preapproved | Sets the status to IMPLEMENT |
The status is AUTHORIZE, and the Authorization Decision field contains the value Rejected | Sends an assignment to the Change owner or owner
group to make a rejection follow-up decision.
|
The status is AUTHORIZE, and the Authorization Decision field is not Approved, Preapproved, or Rejected | If approvers are specified in the approvers
table:
|
The status is IMPLEMENT or IN PROGRESS | Sends an assignment to the Change owner or owner
group to specify whether the Change implementation is complete. Two
choices are provided in the assignment, as follows:
|
The status is COMPLETE | Sets the status to CLOSED for a standard Change, or to REVIEW for a normal or emergency Change. |
The status is REVIEW | Sends a review assignment to the Change owner
or owner group.
|
None of the conditions above match the current situation | A dialog box is displayed, informing you that the status value has no processing defined for it. This occurs throughout the process, each time the current situation does not match the conditions described in this table. |