A Graphical Scheduling project is a work space in the Graphical
Scheduling application where you can produce a schedule. Schedules
that you create in the Graphical Scheduling application help you to
optimize the resources that are used to complete tasks. After you
create a schedule, you save the schedule and resume work in it at
a later time. When you commit a schedule that you have produced, you
bring the schedule information into the Change record.
About this task
A project can be updated or deleted only by the user who
created it.
If you have launched to Graphical Scheduling from
the Schedule tab of the Changes application, some of the schedule
values are automatically populated.
Procedure
- In the Graphical Scheduling application, click the Schedule
tab.
- On the toolbar, click .
- Specify and name and description.
- Populate the appropriate fields for the schedule:
Option |
Description |
Public |
Makes this schedule available to everyone who has access to
any records that the schedule contains. Only users who have the same
authorization as the person who created the schedule are able to see
and manage the full schedule in the Gantt view. |
Preserve Existing Records On Refresh |
Preserves work records in the Gantt view even after the view
is refreshed. For example, records that are closed or canceled after
initially being included in the Gantt view will not be deleted. |
Refresh When Opening Gantt View |
Refreshes the schedule data every time the Gantt view is opened. |
Preserve Schedule Start Dates |
Ensures that the CPM does not change the Start Date of tasks. |
Start Date |
If a date is entered in this field, the schedule starts on
the specified date. The CPM does not schedule any work earlier than
the specified date. This date also is used in cases where the work
records have no target or scheduled dates. If you leave this date
unspecified, the CPM starts with the current date. |
- If you opened the Graphical Scheduling application from
the Go To menu, in the Work Queries section,
find the work records that you want to schedule. You can choose from
existing queries, or create a new one. The records that populate the
schedule are determined by the queries you use. Large queries can
affect system performance. For more information about work queries,
see "Constructing queries."
Option |
Description |
Retrieve a saved work query |
Click Copy Query to produce a list
of work queries from which to choose. Select the query you want to
use. |
Create a new work query |
Click New Row. In the details section
that appears, complete the required fields to specify the details
for the work query. |
- Click Save Schedule.
What to do next
After you create your Graphical Scheduling project, you can
work with the schedule in the Gantt view.