After you detect a conflict that involves an implementation
task, you can resolve the conflict by selecting a conflict-free time
window for the task. You do so in the Graphical Scheduling application.
About this task
To resolve a conflict that has been detected on an implementation
task, perform the following steps:
Procedure
- Open the Schedule tab in the Change that contains the task,
and ensure that the task has an estimated duration. If the estimated
duration is not set, the finish time is automatically set to one hour
after the start time.
- Go to the Graphical Scheduling application and open the
schedule in which the task was scheduled by completing one of the
following tasks:
- Click .
- With the cursor in the Schedule field, press Enter, and select
the applicable Graphical Scheduling project from the record list.
- On the Schedule tab for the Change, click beside Graphical Scheduling Project,
and select Go to Schedule.
- Move the task to one of the conflict-free areas in the
Gantt view.
The scheduled start time for the task
is refreshed to conform to the selected time window. The scheduled
finish time is the scheduled start time plus the estimated task duration.
- Click the Commit Changes button to commit the new task
time to the Change, and click Return to return
to the Change.
- Click Update Conflicts to run conflict
detection again for this Change. After conflict detection runs, the
task no longer is displayed in the Task Conflicts list, because you
have resolved the conflict.